City Council met on 11/17 and the topics covered include:

Community Park: Design Update and Amphitheater Design

For years, residents have requested a new park with amenities like all-weather turf fields, pickleball courts, tennis courts, basketball courts, playgrounds, picnic shelters and an amphitheater to host the City’s ever growing community events. Now, that request is turning into a reality. 40 acres of City owned property east of the roundabout at Scouters Mountain Road and 172nd Avenue will become the home of the new community park.

Design of the park has been ongoing and on Tuesday night, staff and the project architects presented an update to City Council on the progress that has been made. While the major elements and layout are complete, the team is continuing to work on smaller details and will continue to provide updates to City Council in the coming months as they get closer to completion.

During a previous meeting, Council requested to see additional options for the bandshell design that will anchor the amphitheater space. The team presented three new designs, and Council provided direction that they would like to see a blend of the first and third options. The presentation also included an update on project costs and schedule. Construction of the park is scheduled to begin in the summer of 2027.

Community Park Operations & Annual Budget Impacts

Staff provided City Council with a high-level look at current operational cost and revenue projections for the new community park. Staff emphasized that the revenue numbers presented were conservative, and a best estimation given current conditions. Operating costs, revenues, and long-term replacement needs will continue to be refined as planning for the new park progresses.

Public Works Facility Project Update

One of the core services the City provides to the residents of Happy Valley is public works – which includes everything from street sweeping to park and road maintenance, inclement weather response and tree maintenance. As Happy Valley has continued to grow, that work has increased, which requires more equipment and more staff.

Anticipating the growing needs of the public works department, the City began saving money several years ago to build a new public works facility. In 2024 the City purchased land on Armstrong Circle, near 172nd Avenue and Highway 212 to house the new facility.

On Tuesday night, staff and the design team presented the design for the facility to City Council, as well as a project cost estimate and schedule for construction. The funds to build the facility have already been saved, and the project will not require any new tax measures. Construction of the new facility, which will be able to better serve the needs of the community now and in the future, is scheduled to begin in the summer of 2027 and open in the fall of 2028.

Alternative Contracting Strategy: Public Works Facility and Community Park

Oregon state law requires municipalities who are working on large scale capital projects to follow a procurement process colloquially called “design, bid, build”. That means that for a project like the public works facility or the community park the City must first work with a design architect to design the project. Once design is complete then the City would put the project out to bid, to find a contractor who can build the project as it was designed. The City would review bids and be required to select the contractor that can construct the project for the lowest amount of money, regardless of whether they have prior experience on similar projects.

If the City of Happy Valley wants to consider a different procurement process, for example one that considers both contractor experience and low price, then City Council has to pass a resolution approving an alternative contracting method.

On Tuesday night, staff provided Council with a high-level overview of the general contractor procurement options being considered for the community park and public works facility projects. Staff reviewed three separate options and recommended that the Council move forward with a CM/GC procurement process for the two projects. That process allows the City to consider contractor experience and allows the contractor who will construct the project to provide insight during the design phase on constructability, cost estimates, schedules, etc.

Staff will put together a resolution and City Council will vote in December on whether to approve the CM/GC approach.

Happy Valley Park Expansion 

The current public works facility, which is located at the northeast corner of Happy Valley Park off of Ridgecrest Road, will become available for redevelopment once the new public works facility is constructed.

To determine how the site should be redeveloped, City staff will do a study of the site. Staff presented a proposed plan for carrying out the study and sought direction from Council on their priorities for how the space should be used. After some discussion, Council directed staff to study whether the site could include an indoor space that could be used for Parks & Recreation programming and community meetings as well as flexibility for commercial use. Staff will move forward with studying that option, and present updates to Council as they are available.

The full agenda and supporting documents for this meeting can be found online here. Interested residents can sign up to receive public meeting information online, here. City Council meets on the first and third Tuesdays of each month at City Hall. Members of the public are welcome to attend either in person or online.